Wisconsin Street and 35th Street Reconstruction Project


Project Description:

The City contracted the complete reconstruction/resurfacing of Wisconsin Street from 15th Street west just past PVJH and also 35th Street from Wisconsin Street to Valley Drive. This major project  included culvert replacement, overlaying/resurfacing the existing road surface, and work on a sidewalk/walking trail on the north side of Wisconsin Street from 15th Street to PVJH. This project will have many moving parts - so watch for added information on staging of the project.  Thank you for your patience through this much needed improvement in our community!

Timetable:

(Phase 1):  Wisconsin Street and 35th Street Culvert Replacement and Extensions:  Fall, 2021 to June, 2022 (COMPLETED).

(Phase 2):  Wisconsin Street and 35th Street Roundabout Construction and Total Resurfacing of 35th Street and Wisconsin Street  (COMPLETED).


GREAT NEWS!!!!:  WISCONSIN STREET (From 15th Street to PVJH), 35TH STREET (From Valley Drive to Wisconsin Street) AND THE NEW ROUNDABOUT AT PVJH ARE ALL OPEN!!!  


REMINDER:  THERE WILL STILL BE DITCHWORK, SHOULDER WORK, STREET LIGHTING INSTALLED AT THE ROUNDABOUT, SIGNAGE ALONG 35TH AND WISCONSIN STREET, GRADING ALONG THE WALKING TRAIL, ETC..., SO WATCH FOR CONSTRUCTION EQUIPMENT AND WORKERS.