The City is in EARLY DESIGN CONCEPTS/STAGES of the Phase II of the Downtown Reconstruction Project from Ewing Street to Chesnut Street.
Timetable:
PUBLIC INFORMATION MEETING was held May 5 2022 at LeClaire City Hall Council Chambers. Watch for additional public input meetings and information through this planning process.
Preliminary Design: March - December, 2022
Final Design and ROW: June, 2023 - February, 2024
Construction: March, 2024 - December, 2024